Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-ACP Exam Dumps - PMI Agile Questions and Answers

Question # 134

A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?

Options:

A.

Facilitate the team ' s agile retrospective meeting

B.

Guard the team against external distractions

C.

Escalate points of conflict the team cannot resolve

D.

Identify the sequence for developing stories within an iteration

Buy Now
Question # 135

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

Options:

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Buy Now
Question # 136

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative ' s current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

Options:

A.

MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

B.

MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

C.

MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

D.

MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

Buy Now
Question # 137

What should the customer do?

Options:

A.

Expand the Scrum Master ' s role to other projects, while allowing them to support the current project.

B.

Release the Scrum Master, since the team is adequately skilled with agile practices.

C.

Expand the product owner ' s role to serve as the Scrum Master, while providing additional product knowledge.

D.

Increase the functional manager ' s role to act as the Scrum Master, while providing additional information about functional areas.

Buy Now
Question # 138

What should the team do?

Options:

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team ' s target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Buy Now
Question # 139

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?

Options:

A.

Notify the product owner and begin resolution.

B.

Communicate the issue to the team in the next stand-up meeting.

C.

Immediately begin resolution, and communicate it to the team during the retrospective.

D.

Work on the next activity, and communicate it to the team during the retrospective.

Buy Now
Question # 140

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

Options:

A.

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.

B.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 60% of their capacity utilization.

C.

Discuss options to add more people to the team so they can complete the tasks on time and within budget.

D.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 80% of their capacity utilization.

Buy Now
Question # 141

A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.

What behavior would indicate the team is not working well together?

Options:

A.

Team members are sending more emails to the team.

B.

The duration of feedback cycles has increased.

C.

The velocity has increased by having the new team work on items.

D.

New team members requested to move meetings due to time differences.

Buy Now
Question # 142

A product owner is working on a special agile project for the automobile industry. The project team is responsible for all of the issues related to vehicle electronic control units. The team has observed a significant backlog of items in the “In progress ' column (Refer to the kanban board). This accumulation is causing delays in task completion and impacting overall project timelines. The team operates in a dynamic environment where requirements frequently change, and stakeholders demand quick turnarounds.

What should the project team adopt to address this issue and improve task flow, considering all the demands?

Options:

A.

Increase the number of items allowed in the ' In progress " column to accommodate the high volume of tasks and provide flexibility.

B.

Limit the work in progress (WIP) and implement strict policies to encourage team members to focus on completing existing tasks before starting new ones, ensuring a balanced workload.

C.

Move tasks to the ' Done " column regardless of their completion status to give the appearance of progress and alleviate the pressure of the backlog.

D.

Add more team members with varying levels of expertise to handle the increased workload, aiming to accelerate task completion and reduce the backlog in the ' In progress " column.

Buy Now
Question # 143

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

Options:

A.

Collect stakeholder requirements

B.

Conduct an iteration planning meeting

C.

Communicate product backlog items to the stakeholders

D.

Facilitate a product development roadmap workshop

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: May 22, 2026
Questions: 481
PMI-ACP pdf

PMI-ACP PDF

$25.5  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$28.5  $94.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$40.5  $134.99