Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 304

A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.

How should the project manager handle this situation?

Options:

A.

Ask the product owner to create a new entry in the risk management plan regarding likelihood and imped

B.

Review the backlogs from similar projects and understand how change requests were implemented

C.

Ask the product owner to follow the change request process to formalize new requirements

D.

Make sure that the product and sprint backlogs have the required level of documentation and both are visible to the team

Buy Now
Question # 305

A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules

Which two actions should the project manager take with regard to schedule analysis? (Choose two)

Options:

A.

Review with subject matter experts (SMEs) to ensure they have contributed to the schedule development

B.

Evaluate the master schedule and perform fast tracking and task crashing

C.

Look (or gaps in the different schedules to determine which major risks might evolve over time

D.

Review the project schedules to ensure that all tasks end with milestones

E.

Evaluate the schedules for interdependencies to establish the critical path

Buy Now
Question # 306

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?

Options:

A.

Invite the product owner to attend daily standup meetings so they can assessprogress.

B.

Set up a feedback session with the product owner once a week so they can assessprogress.

C.

Instruct the team to refer the product owner to the project manager for information.

D.

Invite the product owner's functional manager to a feedback session to escalate theissue.

Buy Now
Question # 307

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?

Options:

A.

Postpone the required work on the project until school holidays begin

B.

Advise the school to close (or the duration of the project work

C.

Continue the work as planned and inform the school when the project team arrives on-site

D.

Liaise with the school to include nonworking project hours during school start and finish times

Buy Now
Question # 308

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.

How should the project manager plan and manage the project?

Options:

A.

Refuse to manage the project as there is too much risk in developing this kind of project without a product owner.

B.

Define the project's requirements, prepare a long-term detailed plan, and manage the project according to it.

C.

Convince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place,

D.

Agree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.

Buy Now
Question # 309

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)

Options:

A.

Confront the people causing the stress directly with the aim of finding amicable solutions

B.

Seek support from the project management office (PMO) on addressing issues affecting the project

C.

Discuss the possible actions with the project sponsor

D.

Avoid the people causing stress and request a transfer as soon as possible

E.

Talk to the human resources (HR) manager about these concerns

Buy Now
Question # 310

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards

in order to ensure this, what should the project manager define and document?

Options:

A.

Quality

B.

Estimates

C.

Objectives

D.

Requirements

Buy Now
Question # 311

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

Options:

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Buy Now
Question # 312

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

Options:

Buy Now
Question # 313

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

Options:

A.

Ask the accounting manager to delegate a team member who can support the project.

B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,

D.

Begin discussions with other functional managers and meet with the accounting manager later.

Buy Now
Question # 314

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

Options:

A.

Document the risk register in the project charter.

B.

Speak to the customer and add the issue to the issue log.

C.

Review user roles and update the team charter.

D.

Involve the product owner to rewrite the user stories.

Buy Now
Question # 315

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Buy Now
Question # 316

A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Phone conversations

B.

Encrypted emails

C.

Videoconferencing

D.

Chat conversations

Buy Now
Question # 317

An IT project manager has been referred to a new, highly rated vendor that provides quality assurance professional services, The project manager plans to engage the quality assurance vendor on a new project, but their rates do not fit into what was budgeted for the project.

What should the project manager do next?

Options:

A.

Discuss the issue with the management team.

B.

Engage the project stakeholders.

C.

Update the contract with a lower rate,

D.

Engage the procurement team.

Buy Now
Question # 318

A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in

one of the project teams.

What should the project manager do?

Options:

A.

Apply a root-cause analysis on the data breaches.

B.

Ensure that all team members complete the training.

C.

Redesign the training courseware to make it interesting.

D.

Retrain the team members responsible for the breaches.

Buy Now
Question # 319

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.

Organize a brainstorming session with the project team to address the issue.

B.

Advise the project team on the importance of team engagement,

C.

Invest in coaching and training for all project team members.

D.

Escalate the issue with the human resource (HR) department to take action,

Buy Now
Question # 320

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

Options:

Buy Now
Question # 321

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.

Use compression techniques to break down the scope and assign the scope pieces todifferent vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any projectrisk.

C.

Engage in a time and materials (T&M) contract and hire a local vendor to supportdevelopment.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Buy Now
Question # 322

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time

What should the project manager do next?

Options:

A.

Record the issue then refocus the team's efforts on delivering the next set of deliverables

B.

Give the team member a formal warning for the negative impact due to failure to delrver and not meet deadlines

C.

Hold a team meeting to discuss team member commitments and communications

D.

Meet with the team member and work on a development plan for them to avoid missed deliverables in the future

Buy Now
Question # 323

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

Options:

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach

B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using

C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use

D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project

Buy Now
Question # 324

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Options:

A.

Workstream leader and project sponsor

B.

Workstream leader alone

C.

Workstream leader and functional manager

D.

Workstream leader and project management office (PMO)

Buy Now
Question # 325

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

Options:

A.

Facilitate a team-building meeting to help this issue

B.

Allow the team members to remain in their former individual roles

C.

Directly guide the team members on how to perform their tasks

D.

Wait until some iterations are completed to intervene

Buy Now
Question # 326

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

Options:

A.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

Buy Now
Question # 327

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

Options:

A.

Review the benefits management plan

B.

Refer to the lessons learned from the first phase

C.

Consult the project reports from the previous project manager

D.

Collect information from related departments

Buy Now
Question # 328

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

Options:

A.

Schedule a dedicated session to review the team charter.

B.

Set up a meeting with the team member to review the team charter.

C.

Ask another team member to meet with this team member for a discussion.

D.

Send a reminder to the team member about the rule being violated.

Buy Now
Question # 329

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of everyiteration.

B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.

C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.

D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidentialinformation.

Buy Now
Question # 330

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.

What should the project manager do?

Options:

A.

Advise the teams to follow the company’s existing project management approach.

B.

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.

C.

Let a senior team member select the approach that is appropriate.

D.

Insist the teams both follow either a predictive or agile approach.

Buy Now
Question # 331

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

Options:

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

Buy Now
Question # 332

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?

Options:

A.

Schedule a meeting with the director to provide proof of expertise so the clientstakeholders will trust the project team's decision.

B.

Schedule a meeting with the project sponsor to determine if it is appropriate to acceptthe director's request to provide a decision.

C.

Confirm with the director that the client stakeholders will be made accountable for thedecision in the responsibility assignment matrix (RAM).

D.

Ask the client to initiate a change request to make the director accountable for thedecision.

Buy Now
Question # 333

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.

Inform the design team to ensure compliance during the product design phase

B.

Inform the quality team that they need to ensure that the product is in compliance

C.

Ensure that compliance is explicitly mentioned in the relevant requirements

D.

Meet with the team and remind them of the compliance requirements

Buy Now
Question # 334

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

Options:

A.

Maintain a central repository of artifacts with a version control system.

B.

Maintain separate document control via regions to avoid discrepancies.

C.

Develop a document management software for version control.

D.

Facilitate training on version control and project artifacts,

Buy Now
Question # 335

As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved

How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

Options:

Buy Now
Question # 336

In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?

Options:

A.

Submit a change request to leverage previous experience and manage the project using a predictive approach,

B.

Schedule a daily project definition meeting with the team to define the project scope before starting the execution.

C.

Start executing the project as the scope will be defined and redefined throughout the project.

D.

Obtain partial approval from the product owner to baseline the project scope plan before starting the execution.

Buy Now
Question # 337

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.

What should the project manager do?

Options:

A.

Allow the most senior team members to decide the time that works for the team.

B.

Reassess the team's hours collaboratively so that the team is not impeded by the issue.

C.

Discuss the lack of dedication with the team member and their functional manager.

D.

Remove the team member from the project team to be fair to the other members.

Buy Now
Question # 338

A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?

Options:

A.

Schedule training courses to enhance team performance

B.

Add new team members to help the project finalization

C.

Initiate rewards and incentives according to assessment results

D.

Schedule working lunch meetings until the project is complete

Buy Now
Question # 339

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project

What should the project manager do?

Options:

A.

Start planning the project and then request that a PMO be implemented in the organization

B.

Request that the implementation of a PMO be executed in parallel with the project

C.

Provide project management training to only the internal team involved m the project

D.

Provide project management training to the stakeholders and explain their responsibilities

Buy Now
Question # 340

A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?

Options:

A.

Provide the team with a solution that solves the problem.

B.

Coach the team to solve the problem independently,

C.

Discuss the issue with the management team and provide a solution,

D.

Speak with the team lead about the issue and provide a solution,

Buy Now
Question # 341

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

Options:

A.

Allow team members to resolve personal issues without involving the project manager

B.

Arrange and conduct team-building sessions to improve team effectiveness

C.

Obtain feedback from the isolated team member to understand the situation

D.

Get feedback from other team members to understand what led to this situation

E.

Identify the isolated team member as a risk and document the situation in the risk register.

Buy Now
Question # 342

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

Options:

A.

Start with the end user documentation review with the customer and gather feedback

B.

Start with design of the prototype review with the customer and gather feedback

C.

Start with the product prototype development, review with the customer, and gather feedback

D.

Start with the product architecture review with the customer and gather feedback

Buy Now
Question # 343

A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.

Options:

Buy Now
Question # 344

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

Options:

A.

Align with the organization's project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Buy Now
Question # 345

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?

Options:

A.

Review and update the project schedule according to performance

B.

Review the schedule baseline and consider adopting a schedule performance indicator

C.

Develop a lime. cost, and scope tracking method exclusively for this project.

D.

Adopt a formal change management process for the project

Buy Now
Question # 346

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Buy Now
Question # 347

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

Options:

A.

Rebaseline the project schedule to absorb the delay.

B.

Report the delay with rectifying actions to the project management office (PMO).

C.

Notify the project steering committee about the cause of the delay.

D.

Report the delay with rectifying actions to the change control board (CCB) for review,

Buy Now
Question # 348

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?

Options:

A.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.

B.

Schedule a new meeting to evaluate the agreement and negotiate a new one.

C.

Talk with the team member and explain that once the meeting ended, the agreement must be respected.

D.

Meet with the team member and search for the root cause of their behavior.

Buy Now
Question # 349

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

Options:

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.

B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.

C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.

D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.

Buy Now
Question # 350

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Options:

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

Buy Now
Question # 351

A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.

What should the project manager do?

Options:

A.

Assign the marketing executive's tasks to another project team member

B.

Review the executive's declining performance with human resources (HR)

C.

Show empathy and praise the marketing executive's strengths

D.

Make the marketing executive accountable for their work and output

Buy Now
Question # 352

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.

Engaged with the project sponsor to ensure support for the project manager's decision

C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.

Convinced the functional manager to stop the activities that will run beyond the budget

Buy Now
Question # 353

A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager

What should the project manager do first in this situation'?

Options:

A.

Ask the functional manager why a decision was made without consulting them

B.

Use soft skills to influence the team member to slay until the project is completed

C.

Ask the functional manager for an immediate replacement for the team member.

D.

Review the risk management plan and mitigation plan to understand the impact of this issue

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2025 Version)
Last Update: Nov 20, 2025
Questions: 2040
PMP pdf

PMP PDF

$139.65  $399
PMP Engine

PMP Testing Engine

$157.15  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$209.65  $599