Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 354

After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?

Options:

A.

Consult the risk and issue logs.

B.

Initiate a project change request.

C.

Create a baseline impact assessment

D.

Discuss with the project sponsor.

Buy Now
Question # 355

A project team member is struggling to understand a specific requirement. How should a servant leader address this issue?

Options:

A.

Assess and evaluate the team member ' s skills to ensure alignment to the particular requirement and solution

B.

Reassign the requirement to another team member who may have ideas on how to meet the requirement

C.

Assist by connecting the product owner with the team member to discuss what problem is to be solved

D.

Deprioritize the requirement and assign a task tor it to be restated to provide the necessary clarity

Buy Now
Question # 356

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.

Engaged with the project sponsor to ensure support for the project manager ' s decision

C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.

Convinced the functional manager to stop the activities that will run beyond the budget

Buy Now
Question # 357

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information

B.

Scope statement

C.

Issue log

D.

Risk register

Buy Now
Question # 358

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

Options:

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project ' s change control board (CCB),

Buy Now
Question # 359

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

Options:

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Buy Now
Question # 360

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

Options:

A.

Establish the project scope and set clear team objectives

B.

Set performance standards and direction

C.

Hold early kick-off meetings and regular weekly meetings

D.

Select members for their skill or potential

Buy Now
Question # 361

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

Options:

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Buy Now
Question # 362

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add it as an issue in the issue log

C.

Direct the sales team to speak with accounting to resolve the issue

D.

Escalate the issue to the functional manager

Buy Now
Question # 363

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

Options:

A.

Ask the leadership team for help obtaining the needed staff.

B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

D.

Check with human resources (HR) regarding the availability of staff.

Buy Now
Question # 364

After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?

Options:

A.

Develop the team members to work as a cross-functional team.

B.

Ask a functional manager to provide the right team members.

C.

Review the project charter to see if the scope can be modified.

D.

Ask the portfolio manager to reassign the project to another team.

Buy Now
Question # 365

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

Options:

A.

Create an issue log template that will be used to identify and track impediments.

B.

Create a contingency plan in case the project deviates from the initial plan.

C.

Create a schedule management plan to ensure the project meets the delivery date.

D.

Create an assumption log and map assumptions to impediments based on the impact tothe project value.

Buy Now
Question # 366

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

Options:

A.

Review the project scope to align the project teams

B.

Review the resource management plan to align the project teams

C.

Review the project integration plan to align the project teams

D.

Review the work breakdown structure (WBS) to align the project teams

Buy Now
Question # 367

A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer ' s contribution and thinks that the developer deserves a reward.

What should the project manager do?

Options:

A.

Create an opportunity (or the project team to recognize this developer

B.

Send a recognition email to the team and copy management

C.

Reward the developer according to their motivations and interests

D.

Print a recognition certificate and present it to the developer during a meeting

Buy Now
Question # 368

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?

Options:

A.

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.

B.

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.

C.

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,

D.

Determine what methods the team has been trained on and utilize those methods for the project.

Buy Now
Question # 369

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Options:

A.

Work with the product owner to evaluate and prioritize the requirements

B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.

Determine the expected benefits of each requirement to maximize the overall business value

D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

Buy Now
Question # 370

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

Options:

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

Buy Now
Question # 371

In the middle of an iteration, the product owner tells the agile team that the

government has updated legal requirements. This will result in some changes in the product

definition.

How should the project manager handle this situation?

Options:

A.

Review the iteration backlog because the product definition has changed and needs tobe reassessed before continuing the project.

B.

Continue work and ask the product owner to assess the changes and add/remove thestories as needed in the backlog.

C.

Ask a business analyst to assess the changes and then add/remove the stories in thebacklog and prioritize them by business value.

D.

Ask the product owner to add new changes to the bottom of the backlog in order tohandle the modifications as a change request.

Buy Now
Question # 372

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

Options:

Buy Now
Question # 373

A typically high-performing team member has started to demonstrate a performance drop as well as some aggressive behaviors toward other team members in meetings.

The project manager has worked with this individual for many months on this project and has not seen this type of behavior before.

What should the project manager do?

Options:

A.

Discuss the project manager ' s observations with the individual to determine why they are behaving this way.

B.

Discuss the individual ' s behavior with the other team members to determine if they have noticed and know what is going on.

C.

Attend more team meetings to observe the team more closely to determine the root cause.

D.

Discuss their performance with the team member ' s functional manager as well as human resources (HR) and discuss next steps.

Buy Now
Question # 374

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

Options:

A.

Develop a more comprehensive template for the definition of done (DoD).

B.

Increase the percentage allocated for testing each backlog item.

C.

Organize more frequent sprint reviews with a broader audience.

D.

Establish a quality assurance (QA) team separate from the development team.

Buy Now
Question # 375

In a fixed-budget project, the team has received a prioritized list of requirements and has nearly completed the first iteration. The CEO has decided to redirect the team to focus on creating a presentation for their upcoming technology summit. The CEO is not flexible about this request.

Which two actions should the project manager take? (Choose 2)

Options:

A.

Request the CEO to assign some of the functional team members to work on the presentation.

B.

Ask the team to work overtime to make up the time lost by supporting the technology summit.

C.

Determine a new target completion date for the project based on the redirection of the team.

D.

Divide the team to continue working on both the presentation and the project work.

E.

Attempt to complete the presentation work alone so that the timeline is not negatively impacted.

Buy Now
Question # 376

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

Update the issue log and refer to the resource management plan to address the situation.

Ask the team for extra work to fulfill the project commitment.

Reduce the scope of the project and inform stakeholders.

Options:

A.

Ask the sponsor for an experienced team member in the company to help the project team.

Buy Now
Question # 377

A project manager is assigned to a project where a vendor has been engaged to build a new system One week before user acceptance testing (UAT) is scheduled the vendor informs the project manager that they can only deliver half of the promised functions by the UAT start date.

What should the project manager do next?

Options:

A.

Wait until the vendor cannot deliver and then invoke liquidated damages based on the contract

B.

Escalate to management and prepare tor project closure by canceling the contract with this vendor

C.

Adjust the protect schedule to accommodate the current development progress of the vendor

D.

Communicate with the vendor and project team and explore possibilities lor resolving the issue

Buy Now
Question # 378

A development team is struggling to find design documentation for the upcoming sprint. Prior to leaving for vacation, the product owner

communicated that the documentation had been uploaded to the project file repository.

What should the project manager do to address this issue?

Options:

A.

Assign a team member to manage project artifacts.

B.

Audit the effectiveness of the management of project artifacts.

C.

Improve email communication protocols to manage project artifacts.

D.

Investigate new software tools used to manage project artifacts.

Buy Now
Question # 379

A vice president has asked a project manager to support a new urgent project and has informed team members that the project will start soon. The CEO of the company has not yet approved the project to start. The vice president is concerned that the project will not be approved by the CEO on time.

What should the project manager do next?

Options:

A.

Ask the vice president to approve the project charter to kick off the project

B.

Ask the vice president to define who will be the product owner for the project

C.

Investigate if the value and benefits of the project are identified

D.

Start working on the project immediately and determine the scope later

Buy Now
Question # 380

A project manager has been assigned to lead a project with limited funding and resources. During the requirements brainstorming session, several stakeholders request a long list of requirements for a new project, which exceeds the budget.

What should the project manager do first?

Options:

A.

Host a requirements workshop and ask the stakeholders to prioritize the requirements based on critical needs.

B.

Review the requirements and determine which of them can be removed, then advise the stakeholders of the changes.

C.

Meet with the sponsor to obtain their feedback regarding critical requirements in the view of senior management.

D.

Reach out to the sponsor and request additional budget and capacity in order to complete the project.

Buy Now
Question # 381

Drag the items on left side to the matching term within the correct project approach on the right side.

Options:

Buy Now
Question # 382

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.

What should the project manager do?

Options:

A.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.

B.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.

C.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.

D.

Hold the shipment until the rework is completed at the vendor ' s facility to eliminate extra work on-site.

Buy Now
Question # 383

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

Options:

A.

Adapt the resource management plan and ask for financial approval before sending it to the customer.

B.

Assess the impact of the change and review the project management plan for next steps.

C.

Ask the financial manager to delay implementation due to potential project delays and penalties.

D.

Review the project schedule to determine which technique will reduce impact on project duration.

Buy Now
Question # 384

A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of

the team members were stressed due to over commitments.

What should the project manager do?

Options:

A.

Help the team members by organizing regular stress-relieving and team- building sessions.

B.

Request additional resources to continue delivering value while reducing team stress.

C.

Support the team during the planning phase to only commit to what they are able to deliver.

D.

Ask individual team members to plan staggered leave to avoid becoming stressed.

Buy Now
Question # 385

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

Options:

A.

Prioritize the item flagged as high business value and low complexity for this sprint.

B.

Support the team to move both items to the next sprint when the team will know more.

C.

Facilitate the discussion until the team reaches an agreement about the two items.

D.

Prioritize the item flagged as a dependency with low business value and high complexity.

Buy Now
Question # 386

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

Options:

A.

Register an issue and escalate it to the project sponsor.

B.

Invite the stakeholders to discuss a new prioritization.

C.

Estimate the management to replace the customer service manager.

D.

Increase the team capacity to finish the project on time.

Buy Now
Question # 387

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.

Which of the documents was likely missed or outdated?

Options:

A.

Business Documentation

B.

Stakeholder Register

C.

Risk Register

D.

Project Charter

Buy Now
Question # 388

A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.

What should the project manager do?

Options:

A.

Acknowledge the impediments and facilitate their resolutions.

B.

Note the impediments and escalate them to the product owner.

C.

Note the impediments and work on addressing them later.

D.

Assign actions to all stakeholders and oversee their implementation.

Buy Now
Question # 389

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,

the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.

What should the project manager have done to prevent this from happening?

Options:

A.

Reviewed the acceptance criteria and obtained client approval.

B.

Allocated a risk budget for any post-release improvements.

C.

Conducted a pilot to understand the client ' s performance parameters.

D.

Established meetings with the client throughout the project phases.

Buy Now
Question # 390

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project

time lines have slipped, and the staff is overwhelmed .

What should the project manager do to help the company meet their financial objectives?

Options:

A.

Prioritize the projects, giving higher priority to projects that will increase profit.

B.

Make sure the project is fast tracked so that slipped time lines are recovered.

C.

Request that upper management hire additional staff to support the projects.

D.

Ensure that all of the projects are of high quality and are delivered on time.

Buy Now
Question # 391

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be

enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a

problem in the operations department.

What should the project manager do?

Options:

A.

Escalate the situation to the project sponsor.

B.

Free the resource to handle the operations priority.

C.

Ask the manager to submit a change request.

D.

Design a negotiation strategy for this situation.

Buy Now
Question # 392

A project to build a new energy plant was just completed. However, a few days before operation of the plant, the local community protested and closed access to the plant. They argue that an important natural reserve was impacted and prior consultation was not done by the project team.

What should the project manager verify first?

Options:

A.

Stakeholder engagement plan

B.

Risk management plan

C.

Business case

D.

Cost-benefit analysis

Buy Now
Question # 393

A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?

Options:

A.

Review lessons learned from previous projects that used the same team

B.

Review the organizational culture, structure, and governance

C.

Coordinate a meeting to understand the situation and resolve any conflicts.

D.

Coordinate a meeting with regional managers to ask for support

Buy Now
Question # 394

A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?

Options:

A.

Communicate the situation to the team and plan for the necessary training and coaching arrangements

B.

Report the situation back to upper management and request to have the scope changed

C.

Plan to hire more experienced team members and lay off a few of the existing team members.

D.

Communicate the situation to the customer and inform them about potential delays in delivery.

Buy Now
Question # 395

A company wants to increase the commercial value of one of its products in a highly competitive market In order to do this, the company commissions a project to create a prototype The team constructs the prototype incrementally Which action should the project manager take as a priority?

Options:

A.

Emphasize the use of Kanban methodology.

B.

Ensure the project sponsor is aware of the go-to market date

C.

Deliver business value as soon as possible

D.

Implement a plan-do-check-act (PDCA) cycle

Buy Now
Question # 396

An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery

What should the project lead do?

Options:

A.

Escalate the problem to the product owner.

B.

Ask the PMO to review the framework

C.

Request the PMO to define a new framework.

D.

Plan a brainstorming session with the project team

Buy Now
Question # 397

During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.

The customer is asking the project manager for guidance.

What should the project manager do?

Options:

A.

Wait to start the project execution phase until all requirements and acceptance criteria are clear.

B.

Ask the customer to include all of the requirements in the project charter to officially start the project planning phase.

C.

Schedule a brainstorming session and select the top ten most important requirements.

D.

In the planning meeting, focus on releasing a minimum viable product (MVP) quickly and getting feedback from the end users.

Buy Now
Question # 398

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change

What should the scrum master do?

Options:

A.

Create a stakeholder engagement plan

B.

Design a communications management plan

C.

Update the team charter accordingly.

D.

Set up a meeting to discuss accommodations the team will have to make

Buy Now
Question # 399

Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable

What should the project manager do next?

Options:

A.

Check the project budget to verify if there is enough contingency reserve

B.

Review the cost management plan to determine how to address this issue

C.

Tell the team members that more equipment is not part of the project ' s scope.

D.

Submit a change request to increase the budget and buy new equipment

Buy Now
Question # 400

The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders This issue is putting the project schedule at risk

What should the project manager do first to facilitate the approval of project requirements ' ?

Options:

A.

Review the project charter

B.

Perform a stakeholder analysis

C.

Identify the source of the disagreement

D.

Hold a team-building event

Buy Now
Question # 401

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Buy Now
Question # 402

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Options:

Buy Now
Question # 403

A product owner has provided the team with a prioritized backlog for the initial

launch of a new product. After analysis, the team concludes that some work is missing to

support the initial launch and provides this information to the product owner. The product

owner acknowledges the missing work and adds it to the bottom of the backlog. The team is

not happy with the prioritization that the missing work received.

What should the project manager do in this situation?

Options:

A.

Let the project team pull the recommended work from the bottom of the backlog tomaximize value creation.

B.

Analyze and reprioritize the backlog and provide the decision to the product ownerand team.

C.

Recommend the product owner prioritize the missing work higher because it isneeded for the minimum viable product (MVP).

D.

Empower the product owner by supporting the decision and instructing the team to follow the prioritization as provided.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMBOK 7th Version)
Last Update: Jul 5, 2026
Questions: 2196
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599