Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 404

The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

Options:

Buy Now
Question # 405

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

Options:

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Buy Now
Question # 406

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

Options:

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

Buy Now
Question # 407

A company is changing their current business model The change requires implementing a complex project using multiple agile teams.

What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)

Options:

A.

Independent personal testing

B.

Security and performance testing

C.

An experimental approach to cover all possible choices

D.

Story testing

E.

Tests based on behavior and test-driven development

Buy Now
Question # 408

A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?

Options:

A.

Assign resources to coach the business analyst

B.

Ask the business analyst to focus on their work allocation for the needs of the project

C.

Create reports to inform the business analyst about the schedule and project cost

D.

Provide the business analyst with access to the financial and scheduling information

Buy Now
Question # 409

Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?

Options:

A.

Sign the contract as per the original terms but allow the successful bidder to submit a new contract price.

B.

Amend the contract terms and sign a revised contract with the successful bidder.

C.

Retender the entire scope because the terms of the contract have changed significantly.

D.

Discuss the new terms with the successful bidder to assess its impact on the contract price.

Buy Now
Question # 410

A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule, with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.

What should the project manager do first?

Options:

A.

Review the project schedule and ask for the contingency reserve to crash the project.

B.

Meet the project team and stakeholders to identify the root cause of the issue and develop a solution.

C.

Review the lessons learned register with the former project manager in a private meeting.

D.

Meet the project team to assert authority and reassign the project tasks for a timely delivery.

Buy Now
Question # 411

A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of the

requirements. The project manager is concerned about scope creep.

Which action should the project manager take to control the scope?

Options:

A.

Ensure that all key stakeholders agree to the project deliverables and there will be no need for changes.

B.

Accept only those changes to requirements that provide additional value to the project.

C.

Reject all changes that will increase the budget or increase the time line of the project.

D.

Accept only those changes that are approved by the change control board (CCB) prior to being implemented.

Buy Now
Question # 412

A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.

What should the project manager do?

Options:

A.

Register a risk and escalate it to the project sponsor.

B.

Include the responsibility for acquisition with the core team.

C.

Detail the reason for the deliverable delay in the status report.

D.

Invite the stakeholders to discuss prioritization of a new deliverable.

Buy Now
Question # 413

An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project

What should the project manager do?

Options:

A.

Train the team on the new regulations as requested by management

B.

Get commitment from the team to include all of the required regulations

C.

Ask the project sponsor to add more time to the project.

D.

Share with participants the need to focus only on product functionality

Buy Now
Question # 414

A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities

How should the stakeholder be engaged in the project?

Options:

A.

Keep the stakeholder informed and consult with them based on their needs

B.

Involve the stakeholder in governance and decision making

C.

Consult with the stakeholder and increase their level of interest

D.

The stakeholder needs to be made aware of the project progress

Buy Now
Question # 415

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project

What should the project manager do?

Options:

A.

Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.

B.

Stop crashing the schedule

C.

Manage the project sponsor closely and revise the project ' s resource management plan to improve indicators

D.

Use a resource-levelling technique

Buy Now
Question # 416

During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?

Options:

A.

Communicate the concerns to the project management office (PMO) during the weekly project reports

B.

Call for a team meeting to decide if the changes should be included

C.

Initiate the change request to modify the scope and adjust the timelines

D.

Conduct an impact analysis and present the results to the steering committee for approval

Buy Now
Question # 417

A junior team member escalates an issue to the project manager about another

member ' s interpersonal skills causing the team to be less effective.

What should the project manager do first?

Options:

A.

Have the team members resolve the issue on their own.

B.

Highlight the impact of their behavior and motivate the team member to make improvements.

C.

Gather information and find the root cause of the problem.

D.

Document the escalated issue and address it at the end of the project.

Buy Now
Question # 418

A project manager has been assigned to take over an existing software project. The project manager inherited a lean team comprised of key stakeholders, subject matter experts

(SMEs), and senior developers. While reviewing the project status with the team, the project manager observes that the team seems to lack direction and enthusiasm.

What should the new project manager do?

Options:

A.

Ensure everyone performs their assigned tasks as planned.

B.

Organize frequent team building sessions and update the risk register.

C.

Meet with the project sponsor and propose a corrective action for the project.

D.

Encourage participation in decision making and empower the team.

Buy Now
Question # 419

The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

Options:

A.

Product owner

B.

Change control board (CCB)

C.

Project sponsor

D.

Project manager

Buy Now
Question # 420

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

Options:

A.

Give team members more authority to make decisions.

B.

Perform team-building activities and enhance collaboration.

C.

Identify the team members who are impacting low morale.

D.

Coach the team members on agile processes and knowledge.

Buy Now
Question # 421

Having managed a similar project while working with previous stakeholders, a

project team decided to use the same report format they used in the earlier project.

However, stakeholders new to the project are not fully comprehending the status of the

project based on the reports that are being circulated.

How should the project manager address this concern moving forward?

Options:

A.

Add the issue to the issue log and determine the corrective action.

B.

Create a fishbone diagram to determine the root cause for the misunderstanding.

C.

Employ Monitor Communications techniques, which may eventually trigger changes to the communications management plan.

D.

Share the communications management plan and remind all stakeholders of the agreed-upon reporting templates.

Buy Now
Question # 422

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

Options:

A.

Document the lessons learned and implement improvements in the next sprint

B.

Facilitate a daily standup with the team to track the implementation of changes

C.

Organize a demonstration of the changes in the enterprise system

D.

Request that all team members think of ideas to improve processes.

Buy Now
Question # 423

An organization in a regulated industry has decided to switch from a predictive to

an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,

and the project manager is still accountable for the project outcomes. During the fourth sprint

demo, the customer notices that a feature is not compliant with the regulations.

What should the project manager do?

Options:

A.

Have the team consult with the compliance officer to update the definition of done(DoD) for the user stories in the past sprint.

B.

Have the product owner consult with the change control board (CCB) to have thenecessary compliance requirements implemented.

C.

Have the scrum master organize a weekly meeting with the compliance officer, theproduct owner, and the project team.

D.

Have the product owner review the user stories in the product backlog with thecompliance officer on a regular basis to identify any gaps.

Buy Now
Question # 424

A project manager is assigned to a technical research project. The project team has

already been assigned, and the main subject matter expert (SME) sends the project

manager a list of the technical skills required for the execution of this project.

What should the project manager do next?

Options:

A.

Send the list to the project team and ask them to get training on the required skills.

B.

Ask the functional manager to review the resource pool and recommend the right individuals to join the team.

C.

Discuss the list with the project sponsor to confirm that the resources have the required skills.

D.

Meet with the project team to understand their skills and identify potential gaps and training requirements.

Buy Now
Question # 425

A project manager is leading a product development project that requires high involvement from several stakeholders. What should the project manager do to ensure this involvement?

Options:

A.

Evaluate the engagement needs of stakeholders.

B.

Distribute weekly status emails to stakeholders.

C.

Engage the sponsor on the behavior of stakeholders.

D.

Conduct weekly update meetings with stakeholders.

Buy Now
Question # 426

Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)

Options:

A.

Host a special meeting to talk about what happened.

B.

Escalate the issue to human resources (HR).

C.

Review the lessons learned document with the team.

D.

Conduct a team-building workshop.

E.

Discuss this incident in the project review meeting.

Buy Now
Question # 427

local company is developing a new product and. for the first time, using a remote

team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project ' s

outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

Options:

A.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

B.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

C.

Review lessons learned from previous projects and organizational process assets (OPAs).

D.

Determine the communication needs, environment, and tools to get the message across.

Buy Now
Question # 428

An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager

do with many tasks still open on the Kanban board?

Options:

A.

Decompose the item immediately and begin work.

B.

Discuss the impact of starting the item with the team.

C.

Finish the small tasks in progress before decomposing the item.

D.

Communicate the impact with the project sponsor.

Buy Now
Question # 429

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

Options:

A.

Circulated the project charter

B.

Assessed the organizational culture

C.

Determined the level of maturity of the employees

D.

Communicated the project schedule

Buy Now
Question # 430

A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?

Options:

A.

Request the project sponsor prioritize and if necessary, allocate additional budget so the team can work on a single project

B.

Provide an incentive plan so the team members will work more unaccounted hours on multiple projects

C.

Brainstorm with the team members on how they can deliver on multiple projects within the given budget

D.

Instruct the team members to spread evenly across projects so mistakes will not occur within the current budget.

Buy Now
Question # 431

A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

Options:

A.

Encourage better team communication by positioning team members closer together.

B.

Implement a project management information system (PMIS)

C.

Update the communications management plan to ensure correct delivery of the latest version

D.

Restrict team members from sending the requirements documents via email

Buy Now
Question # 432

A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member ' s agile experience with the existing team members.

What should the project manager do to integrate the new team member effectively?

Options:

A.

Train the new team member in the predictive project management approach.

B.

Acknowledge that hiring this new employee is a risk to the existing team

C.

Set expectations with the new team member and explain what is needed

D.

Meet with all team members and explain the new employee ' s position.

Buy Now
Question # 433

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

Options:

A.

Assign the tasks to the resources based on their expertise.

B.

Ensure that the priority of each task is clear to the team.

C.

Ask the team to self-organize and manage the work assigned.

D.

Tell the team which task to focus on at the next daily standup.

Buy Now
Question # 434

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?

Options:

A.

Talk to the supervisor to tone down their approach and attitude.

B.

Provide a just-in-time training to the technician to improve their skill set.

C.

Use a direct, collaborative approach with the technician and supervisor.

D.

Replace the technician with a high performing resource as time is critical

Buy Now
Question # 435

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

Options:

A.

Contact the human resource (HR) department for a solution.

B.

Speak with the key team member to clarify the situation.

C.

Conduct a meeting with the team to deliberate on a decision.

D.

Suspend the team member until further notice.

Buy Now
Question # 436

Drag the technical practices on the left to the scenario on the right.

Options:

Buy Now
Question # 437

A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.

What should the project manager have done to avoid this situation?

Options:

A.

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred

B.

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress and regularly escalated delays

C.

Met with the team, allowed team members to make decisions about what to do and established performance goals

D.

Conducted routine meetings and identified team members who are under performing

Buy Now
Question # 438

During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?

Options:

A.

Refine and estimate the enhancement so the size is known.

B.

Add it to the product backlog to be completed in the future.

C.

Start working on the enhancement for the customer immediately.

D.

Ask the product owner to prioritize the item with the customer.

Buy Now
Question # 439

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

Options:

A.

Change the approach with the team.

B.

Meet with an agile coach to handle this issue.

C.

Analyze the level of the team ' s agile maturity.

D.

Support the team members ' growth and development.

Buy Now
Question # 440

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.

Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.

What should the project manager do next?

Options:

A.

Escalate the issue to a higher authority.

B.

Suspend the two key team members immediately.

C.

Put the issue on the agenda for the next team meeting.

D.

Reassign one of the key team members to a different task.

Buy Now
Question # 441

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)

Options:

A.

Contact the team member ' s functional manager and invite them to the next retrospective

B.

Meet with the entire team to review the ground rules about safe environments

C.

Meet with the product owner to talk about the situation.

D.

Contact the team member to explain what information can be shared outside the team

E.

Meet with the sponsor to review the situation.

Buy Now
Question # 442

A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.

What should the project manager have done to avoid this?

Options:

A.

Used communication tools, such as video conferencing so different offices could communicate.

B.

Learned more about how each team member prefers to communicate before assigning project work

C.

Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

D.

Ensured that the project would be the highest priority for all team members

Buy Now
Question # 443

A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase

How should the business increase the value of the project?

Options:

A.

Quantify the expected tangible and intangible benefits in the benefits management plan for each phase

B.

Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.

C.

Consult with experts on methods to reduce costs and increase the financial value of the project

D.

Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner

Buy Now
Question # 444

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

Options:

Buy Now
Question # 445

During the course of a project the project manager ' s immediate director is communicating directly with the client to approve changes without the project manager ' s knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?

Options:

A.

Communicate directly with the director and inform them of the communications management plan

B.

Communicate directly with the client stating that any scope changes must go through the project manager

C.

Review the stakeholder engagement plan and put in place any existing actionsaccordingly

D.

Discuss the issues with the project team and let them know that the project manager will handle scope changes

Buy Now
Question # 446

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

What should be the priority order in the product backlog?

Options:

A.

Risk3, Risk 1, Risk2, Requirements, Requirement 1. Requirement2

B.

Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2

C.

Requirements, Requirement 1, Requirement2

D.

Requirement 3. Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2

Buy Now
Question # 447

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

Options:

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

Buy Now
Question # 448

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

Options:

A.

Create a change request to discuss with the change control board (CCB).

B.

Request additional budget for contingency.

C.

Perform a risk identification process with the project team.

D.

Consult with the project stakeholders.

E.

Discuss the possible impacts with subject matter experts (SMEs).

Buy Now
Question # 449

A transportation company is transforming its operational processes and the mam system this company uses to move freight The scope statement is in place An iterative delivery approach has been agreed by all stakeholders. What does the project manager need to do next to help the team understand the work that needs to be done?

Options:

A.

Work with the team to decompose the scope into a WBS and work packages in order to create required deliverables and timelines.

B.

Work directly with stakeholders on the work breakdown structure (WBS) and assign tasks with a required timeline for each team member to start the work.

C.

Create the requirements management plan to outline how project requirements will be collected analyzed and documented and then assign requirements to team members

D.

Start working on the project management plan with work packages, a detailed schedule, and work assignments for team members

Buy Now
Question # 450

A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty

What should the project manager have done to avoid this situation?

Options:

A.

Ensured the team charter was developed by the team members

B.

Ensured the team members are fully supportive of all decisions.

C.

Distributed the project charter to all team members.

D.

Used a charismatic leadership style

Buy Now
Question # 451

A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders ' concerns?

Options:

A.

Send communications for clarification so there is a full understanding about the situation.

B.

Demonstrate the performance indexes and recommend corrective actions to the stakeholders

C.

Schedule a kick-off session to explain the problems of the project and gain approval and support

D.

Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders

Buy Now
Question # 452

A project manager is responsible for providing a budget estimate for a long-term project that will be executed over several years. Which essential task should the project manager implement at this phase?

Options:

A.

Include key risks in the cost baseline.

B.

Perform an analogous estimate.

C.

Perform a bottom-up estimate.

D.

Include projected inflation rates.

Buy Now
Question # 453

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMBOK 7th Version)
Last Update: Jul 5, 2026
Questions: 2196
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599