A business improvement opportunity to reduce energy usage has been identified.
The project manager has assembled a team that includes site engineers to deliver this project.
However, due to production imperatives, the site engineers may not be fully focused on the
project.
How should the project manager manage the team?
A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback
What should the project manager do to resolve the issue?
A key resource is newly assigned to a project. The project manager and the resource
did not get along well in a previous project. This resource is needed to ensure the completion
of a major component for the project.
What should the project manager do?
Vendor A submitted a bid for US$500,000. There is a 65% probability that the
vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come
in ahead of schedule for a savings of US$50,000.
What should the project manager determine as the value of the vendor's bid?
A project has been running successfully for 2 months. At a regular project meeting,
the team raises several potential obstacles to future progress. The obstacles include vendor
delivery performance, technical performance of a subsystem, and conflict with another division of the organization.
What should the project manager do next?
An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project
How should the agile leader ensure successful delivery?
An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives
What should the project manager do?
A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.
What should the project manager do to ensure effective communication throughout the project?
A project manager working on a large-scale network implementation is frustrated
with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.
What should the project manager do first to proceed with this change?
A project manager has been assigned with initiating a large project to deliver complex equipment Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.
Which approach should the project manager choose for this project?
A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable
What should the project manager do to resolve this?
A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule
What should the project manager do?
During a meeting with a customer, it was determined that participants of the meeting
had different draft versions of an important design document. What should the project
manager do first to ensure that this does not happen again?
An agile team has started a new project. When should the project manager organize their first team retrospective?
A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage
What should the project manager do?
A project team is executing a project to replace an existing system with a new one.
A new project manager has been hired and observes that the team consist of professionals
who have worked with the older system, and others who have little previous experience.
What should the project manager do to ensure project success?
Toward the end of a protect the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?
A project sponsor asks the project manager to explore a hybrid approach for a new
project. The product manager for this project has already prepared a detailed specification for the product.
What should the project manager do to proceed with the project management plan?
A project with multiple teams recently transitioned from a predictive approach to agile
as requested by the product owner. Midway through implementation, a team member noticed
there was no technical capability to support the current business requirement; therefore, the
project will need to be reworked and the issue needs to be communicated to all stakeholders.
What should the agile project lead have done to avoid this situation?
A project to implement a new online landing platform has started After the first sprint, the project sponsor requested a change. What should the project manager do next?
During the setup of an agile project, the product owner expressed clear interest in
having features released during product development over having the product completed in
one year. What should the project manager do?
During the sprint planning of a project, the team members have a disagreement
about the comparative size of the backlog items and if they would fit into the next sprint.
Considering a hybrid approach, what should the project manager do?
During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer's request will affect the sales department's budget and forecast.
In order to reach a consensus and have a successful project completion, what should the
project manager do first?
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?
A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?
A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.
How should the project manager address this?
During the forming phase of a project team a project manager implements several team-building initiatives and decides it would be fun to have improvisations theater activities. After the sessions the project manager received feedback from some key team members who felt that although the activity was fun it was not appropriate for the purpose of team building.
What should the project manager have done to avoid this negative feedback'?
A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?
At the end of a project, one of the suppliers is facing financial difficulties and is
pushing the project manager to obtain financial, legal, and administrative approval in order to
communicate formal project closure and ensure the transfer of liability. What should the
project manager do next?
Throughout an entire project, the project manager took notes at every meeting with
team members. These notes provided useful insights from key stakeholders, which later
resulted in increased value to the project. The project manager thought it would be helpful to
keep these notes as a future reference for other project managers within the organization.
Where should the notes be located?
During the execution of a construction project, the project sponsor asks to make
changes to the floor plan by adding a minimal storage room. The sponsor insists on making
this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.
What should the project manager do?
A project manager is leading a project that is implementing an assembly line.
During the quality review meeting, a team member reports an issue stating that the product
being developed has discrepancies with the one requested by the customer.
What should the project manager do?
A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?
The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.
What should the project leader do to solve this situation?
One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.
What should the project manager do?
A new project manager has been assigned to an environmental project. After
reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.
Why is this situation problematic?
A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations
One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?
A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.
What should the project manager do to address this concern?
A project team consists of members based in country A and subject matter experts
(SMEs) based in country B with a 12-hour time difference. What can the project manager do
to improve interactions between the team members in both countries?
A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?
Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.
What should the project manager propose?
A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.
What should the project manager ask the team to do?
A customer asks the project manager about opportunities to create business value.
What should the project manager do first in order to provide the customer with an appropriate
response?
A key project team member has exhibited high interest in a project. The input from
this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.
What should the project manager do?
While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.
How should the project manager handle this situation?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?
A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.
How should the project manager ensure the acceptance criteria are ret?
A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce
the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December
might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.
What should the project manager do about this risk?