Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 454

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

Options:

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

Buy Now
Question # 455

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

Options:

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Buy Now
Question # 456

A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.

Which action should the project manager take?

Options:

A.

Empower team members to participate in decision-making and take ownership of actions.

B.

Implement a flexible work schedule policy to eliminate the time zone problems among stakeholders.

C.

Encourage team members to network so that they know each other's cultural backgrounds.

D.

Provide a relaxed work schedule policy and encourage team members to work from home.

Buy Now
Question # 457

At the end of the last iteration, the customer rejects the deliverables since they did

not meet the customer's expectations. What should the project manager have been done

to prevent this situation?

Options:

A.

Involved the customer more in the planning process for the project, and ensuredagreement on the proceedings.

B.

Included all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.

C.

Provided the customer with the backlog and the specified user stories at the beginning of the iteration.

D.

Developed the DoD in close cooperation with all stakeholders to ensure their expectations were included.

Buy Now
Question # 458

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

Options:

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Buy Now
Question # 459

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

Options:

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

Buy Now
Question # 460

A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?

Options:

A.

The communications management plan was not used by all stakeholders.

B.

Organizational assets were not available to back the rationale.

C.

Relative estimation by the team resulted in two estimates.

D.

The use of the Monte Carlo method can result in different estimations.

Buy Now
Question # 461

A project manager is meeting with the project sponsor regarding a new project.

The project manager tells the sponsor that, as part of the communications management

plan, a weekly email will be sent with the status of the project, so the sponsor can be

informed of the progress. The sponsor indicates that the email is not necessary because

they will ask for a status update whenever it is needed.

What should the project manager do next?

Options:

A.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

B.

Agree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

C.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

D.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

Buy Now
Question # 462

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Buy Now
Question # 463

Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?

Options:

A.

Reaffirm the required project obligations directly with the team member. oy

B.

Ask the team member to explain the reason for the absences.

C.

Assess the impact of the team member's absence on the task involved.

D.

Send a formal letter to the team member stating that their absences are noted.

Buy Now
Question # 464

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

Options:

A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Buy Now
Question # 465

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

Options:

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

Buy Now
Question # 466

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

Options:

A.

Ask the team leader to assign other resources.

B.

Update the issue log.

C.

Include this in the risk register.

D.

Escalate the issue to the functional manager.

Buy Now
Question # 467

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

Options:

A.

Follow the organization's process and deliverables for predictive projects, even ifthey compromise the agility and performance of the project.

B.

Use the risk register to document all of the compliance vulnerabilities generated bythe project so that all decisions are well documented and approved by stakeholders.

C.

Meet with the project management office (PMO)/compliance entity to work onprocess tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Buy Now
Question # 468

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

Options:

A.

Report the violation to the change control board (CCB) and seek comprehensiveapproval for these modifications.

B.

Update the change management plan to define the level of control required forthese types of modifications.

C.

Ask the quality control team to evaluate the modifications, but take no actionbecause the associated quality risks are insignificant.

D.

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

Buy Now
Question # 469

A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team's productivity.

What should the project manager do next?

Options:

A.

Review the iteration duration with the team.

B.

Discuss the issue in the next retrospective.

C.

Encourage the team to improve their performance.

D.

Reduce the iteration backlog.

Buy Now
Question # 470

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

Options:

A.

Look for processes that cause bottlenecks and slow down the team's agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

Buy Now
Question # 471

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

Options:

A.

Hire a company to advertise the project and company through a media outlet.

B.

Prepare a report outlining the organizational structure and project parameters.

C.

Take the stakeholders out informally and verbally brief them about the organization and project.

D.

Ask a team member to directly address the information needs of the stakeholders.

Buy Now
Question # 472

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

Options:

A.

Ask the team.to accelerate the iterations and avoid interruptions.

B.

Discuss the problem with the team and decide how to do the work together.

C.

Verify team performance and ask for improvement during daily standup meetings.

D.

Recommend that the project sponsor increases the budget to bring new resources.

Buy Now
Question # 473

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?

Options:

A.

Escalate to the project steering committee.

B.

Invite the finance department to the next project demo.

C.

Review the project requirements.

D.

Use the currently available resources.

Buy Now
Question # 474

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Buy Now
Question # 475

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.

What should the project manager have done?

Options:

A.

Conveyed task completion information to accounting

B.

Closed the procurement process properly

C.

Completed the transition process

D.

Performed administrative closure of the project

Buy Now
Question # 476

During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?

Options:

A.

Refine and estimate the enhancement so the size is known.

B.

Add it to the product backlog to be completed in the future.

C.

Start working on the enhancement for the customer immediately.

D.

Ask the product owner to prioritize the item with the customer.

Buy Now
Question # 477

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

Options:

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

Buy Now
Question # 478

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

Options:

A.

Give team members more authority to make decisions.

B.

Perform team-building activities and enhance collaboration.

C.

Identify the team members who are impacting low morale.

D.

Coach the team members on agile processes and knowledge.

Buy Now
Question # 479

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

Options:

A.

Document the lessons learned and implement improvements in the next sprint

B.

Facilitate a daily standup with the team to track the implementation of changes

C.

Organize a demonstration of the changes in the enterprise system

D.

Request that all team members think of ideas to improve processes.

Buy Now
Question # 480

A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?

Options:

A.

Log a risk in the risk register and work with the new team member to mitigate it

B.

Motivate the new team member to perform.

C.

Share project documents with the new team member.

D.

Offer cross-training and mentoring to the new team member

Buy Now
Question # 481

A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.

What should the project manager do first?

Options:

A.

Organize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.

B.

Decline the request politely since the issue, although critical, is not the responsibility of the project team.

C.

Allocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.

D.

Inform the customer that they should contact the sales manager and submit a formal request for a quote.

Buy Now
Question # 482

An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

Options:

A.

Convinced the critical resource to remain on the project.

B.

Requested an experienced resource as a replacement

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

Buy Now
Question # 483

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.

How should the project manager approach this situation?

Options:

A.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.

B.

Continue to work on the project until the stakeholders and management come to a decision.

C.

Socialize with the stakeholders to better understand their needs and reset expectations.

D.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.

Buy Now
Question # 484

A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?

Options:

A.

Contact the functional managers to request substitutes for the conflicting team members.

B.

Send a warning to both team members indicating that if the issue continues, both will be removed from the project.

C.

Schedule a meeting with both team members to understand the issue and facilitate a solution that satisfies both parties.

D.

Escalate both team members to their respective functional managers and let them take the appropriate actions

Buy Now
Question # 485

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

Options:

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Buy Now
Question # 486

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders

What document should the project manager use to communicate these requests?

Options:

A.

Risk log

B.

Change log

C.

Backlog

D.

Issue log

Buy Now
Question # 487

A contractor delivering construction services to a company is using agile principles

to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design

changes or performing rework.

What should the project manager do to minimize the cost?

Options:

A.

Put the project on hold until all definitions are ready in order to avoid rework.

B.

Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.

C.

Capture the engineers' feedback at the daily meeting and communicate it to the product owner.

D.

Cancel the project release resources, then start again when all the definitions are ready.

Buy Now
Question # 488

A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project

How should the project manager proceed?

Options:

A.

Consult the project sponsor and request their feedback

B.

Consult the product owner and request a complete prioritization session

C.

Consult a senior project manager within the organization and request their expert judgement

D.

Consult a senior developer within the organization and request their input.

Buy Now
Question # 489

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

Options:

A.

Create a change request to discuss with the change control board (CCB).

B.

Request additional budget for contingency.

C.

Perform a risk identification process with the project team.

D.

Consult with the project stakeholders.

E.

Discuss the possible impacts with subject matter experts (SMEs).

Buy Now
Question # 490

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

Options:

A.

Ensure that the requirements for the project are understood and that the objectivesare verified before approval of an agreement.

B.

Inform the project sponsor that once the agreement has been signed, there cannotbe any changes to the scope of the project.

C.

Notify the project sponsor that the project manager cannot be involved in theagreement negotiation process.

D.

Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

Buy Now
Question # 491

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

Options:

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments

B.

Incremental delivery and frequent backlog refinement based on user feedback

C.

Iterative development and collection of frequent feedback from project team members

D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented

Buy Now
Question # 492

A few developers have submitted their resignation after completing their annual review and receiving their annual bonus. The project manager cannot find replacements for all of the developers in time to meet the project's deadline.

What should the project manager do?

Options:

A.

Request additional budget to recruit more developers.

B.

Lower the recruitment criteria.

C.

Log the issue in the issue log.

D.

Analyze the impact and inform the stakeholders.

Buy Now
Question # 493

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?

Options:

A.

Discuss with the product owner that the user story will not be completed this iteration.

B.

Meet with the team member's functional manager to try to remove the impediment.

C.

Tell the project team member not to work on the production issue and to inform their manager.

D.

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.

Buy Now
Question # 494

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

Options:

A.

Modify the daily standup meetings to include project status reporting.

B.

Escalate the issue to the change control board (CCB) and ask for advice.

C.

Adopt the role of supporting and empowering the project team to do the work.

D.

Change the approach for the project to a predictive approach.

Buy Now
Question # 495

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?

Options:

A.

Stop the meeting and reschedule for another time with a more concise presentation.

B.

Set up information review sessions before reconvening another approval session.

C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.

D.

Obtain approval as fast as possible and close the meeting.

Buy Now
Question # 496

The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.

What should the project manager do first in this situation?

Options:

A.

Meet with the project sponsor as soon as possible to discuss the matter further

B.

Update the issue log to make the project team aware and to develop a strategy

C.

Create a stakeholder engagement plan to help the team formulate a response

D.

Provide the specifications to the project sponsor with some information removed

Buy Now
Question # 497

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Options:

A.

Continue with the sprint as the progress shows buffers for potential interruptions.

B.

Ask the product owner if some low-priority stories could be cut from the sprint.

C.

Continue with the sprint work as planned and keep monitoring.

D.

Ask the project team to select any additional stories as they have additional capacity than planned.

Buy Now
Question # 498

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

Options:

A.

Consider cultural differences among stakeholders.

B.

Conduct an integration meeting among all stakeholders.

C.

Schedule communication training for management-level stakeholders.

D.

Understand how political aspects can affect the project.

Buy Now
Question # 499

An organization in a regulated industry has decided to switch from a predictive to

an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,

and the project manager is still accountable for the project outcomes. During the fourth sprint

demo, the customer notices that a feature is not compliant with the regulations.

What should the project manager do?

Options:

A.

Have the team consult with the compliance officer to update the definition of done(DoD) for the user stories in the past sprint.

B.

Have the product owner consult with the change control board (CCB) to have thenecessary compliance requirements implemented.

C.

Have the scrum master organize a weekly meeting with the compliance officer, theproduct owner, and the project team.

D.

Have the product owner review the user stories in the product backlog with thecompliance officer on a regular basis to identify any gaps.

Buy Now
Question # 500

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?

Options:

A.

Provided copies of the stakeholder engagement plan to all team members.

B.

Defined the roles and responsibilities of the team members.

C.

Updated the communications management plan.

D.

Established ground rules for the team

Buy Now
Question # 501

An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?

Options:

A.

Ask for additional team members to maintain the velocity

B.

Implement a checkpoint in the iteration to verify if the team is on track

C.

Conduct a focused retrospective to help the team to discover the root cause

D.

Ask the team to have a lower commitment for the next iteration

Buy Now
Question # 502

A project manager is assigned to a new project. The project management office

(PMO) and the project manager agree that this is the right opportunity to include daily

standup meetings. The project team has never used such tools, and a few members are

challenging the decision.

What should the project manager do in this situation?

Options:

A.

Engage an external vendor to perform the design phase under an iterative approach.

B.

Request that new team members familiar with iterative approaches be assigned to this project.

C.

Update the project schedule to consider a daily standup as part of the project design phase.

D.

Define the ground rules, responsibilities, and conflict management strategies.

Buy Now
Question # 503

Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)

Options:

A.

Host a special meeting to talk about what happened.

B.

Escalate the issue to human resources (HR).

C.

Review the lessons learned document with the team.

D.

Conduct a team-building workshop.

E.

Discuss this incident in the project review meeting.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMBOK 7th Version)
Last Update: Apr 6, 2026
Questions: 2191
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599