Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 454

A project team has recently finished a sprint for developing two features for a fleet management system Although the team delivered the required features, they encountered several issues and conflicts during the sprint. Team members were upset about this experience and are now showing a lack of motivation due to what has occurred.

What can the project manager do to help increase the team's motivation and engagement with the project?

Options:

A.

Review sprint progress with the project team members

B.

Set up one-on-one meetings with the project team members

C.

Review sprint planning procedures with the project team members

D.

Perform a sprint retrospective with the project team members

Buy Now
Question # 455

During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?

Options:

A.

Ask the new team member to follow the team ground rules.

B.

Ask an experienced team member to identify a replacement

C.

Ask the new team member to reassess their own capabilities

D.

Ask an experienced team member to coach the new team member

Buy Now
Question # 456

During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?

Options:

A.

Ask upper management for more funds and update the project budget

B.

Revise the project scope accordingly to cope with the budget changes

C.

Update the risk register and project log. and manage the budget closely.

D.

Submit a change request to accelerate the project as requested

Buy Now
Question # 457

During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?

Options:

A.

Update the communication styles for enrolled team members in the communications management plan.

B.

Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)

C.

Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.

D.

Update the resource calendar for enrolled team members in the resource management plan

Buy Now
Question # 458

A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?

Options:

A.

Assign resources to coach the business analyst

B.

Ask the business analyst to focus on their work allocation for the needs of the project

C.

Create reports to inform the business analyst about the schedule and project cost

D.

Provide the business analyst with access to the financial and scheduling information

Buy Now
Question # 459

The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.

What should the project manager do?

Options:

A.

Arrange a meeting with the managers and try to reach an agreement.

B.

Communicate with the project sponsor regarding the need to resolve the conflict between the managers.

C.

Evaluate the impact of the delay on the project and look for alternatives to create a remediation plan

D.

Meet with both teams and their managers and try to figure out the root cause of the conflict

Buy Now
Question # 460

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

Options:

A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Buy Now
Question # 461

At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?

Options:

A.

Project audit

B.

Lessons learned

C.

Organizational process assets

D.

Procurement audit

Buy Now
Question # 462

A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.

What should the project manager do?

Options:

A.

Conduct a performance review and define and document the goals for the team member.

B.

Clarify decisions and request that the project team follows the project manager's decisions.

C.

Understand what the team member wants and find possible opportunities to address it.

D.

Remove existing ground rules and create new ground rules that support the project manager.

Buy Now
Question # 463

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?

Options:

A.

Talk to the supervisor to tone down their approach and attitude.

B.

Provide a just-in-time training to the technician to improve their skill set.

C.

Use a direct, collaborative approach with the technician and supervisor.

D.

Replace the technician with a high performing resource as time is critical

Buy Now
Question # 464

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

Options:

Buy Now
Question # 465

During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?

Options:

A.

Conduct an expert judgment evaluation.

B.

Review the quality management plan

C.

Update the lessons learned register

D.

Review the risk management plan

Buy Now
Question # 466

After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features

What should the project manager do to avoid this in the future?

Options:

A.

Set up requirements-gathering sessions with all key stakeholders to evaluate the scope once again and reprioritize the backlog based on the sessions.

B.

Schedule adequate sprint demos to gather early feedback from the stakeholders and adapt the plan accordingly

C.

Incorporate design thinking practices into the project life cycle to better understand the product's personas and be more effective to match their needs.

D.

Evaluate the team's skills to look for someone with experience in product design and assign that person the task of rebuilding the product interface

Buy Now
Question # 467

A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted What approach should the project manager take to remove this impediment?

Options:

A.

Follow a predictive approach in order to obtain formal acceptance of each deliverable

B.

Work with the product owner to define the minimum viable product(s)

C.

Reinforce the negotiation and soft skills of the team through training

D.

Develop and monitor a plan with due dates to reduce the time of completing the product

Buy Now
Question # 468

The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action

What two actions should the project manager take'? (Choose two)

Options:

A.

Discuss with the construction team alternatives on moving the new train station to another location.

B.

Publish information on the city’s website about the benefits that the new tram station will bring

C.

Have a meeting with the mayor and explain the importance of the new train station to the city.

D.

Conduct regular meetings with the neighbors to get their buy-in for the project

E.

Register this situation as a risk and develop a mitigation plan

Buy Now
Question # 469

A company has decided to implement a new archiving system A data breach occurred during the implementation of the project

What should the project manager do first?

Options:

A.

Implement the planned risk response to handle the issue.

B.

Review possible alternative documentation methods with team

C.

Update the risk register with the risk and proposed impact.

D.

Ask the team to fix the system to resolve the issue

Buy Now
Question # 470

A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?

Options:

A.

Sort conflicts into two groups: positive and negative

B.

Place conflicts into categories: structural and interpersonal.

C.

Place conflicts on a shared conflict list and ensure it is visible

D.

Review conflicts during daily Scrum so they are handled in a timely manner

Buy Now
Question # 471

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?

Options:

A.

The project is an information technology project and has minimal impact to the organization

B.

The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).

C.

The project scope is well defined and the requirements are prioritized

D.

The project team has a colocated space and is capable of working together

Buy Now
Question # 472

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

Options:

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

C.

The project manager should allow the resources to periodically choose on which team they would like to work.

D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

Buy Now
Question # 473

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Buy Now
Question # 474

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?

Options:

A.

Ensured the risk tolerance of the company was property updated

B.

Implemented the communications management plan properly

C.

Implemented the stakeholder engagement plan correctly.

D.

Provided a proper risk response

Buy Now
Question # 475

A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule

What should the project manager do to keep the project on schedule while still meeting project objectives'?

Options:

A.

Collaborate with the change control board (CCB) to review the scope and submit any change requests

B.

Submit a change request to the CCB and update the schedule

C.

Update the scope and add more resources to the project

D.

Update the scope and move on to the next project milestone

Buy Now
Question # 476

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

Options:

A.

Escalate this issue to senior management, as the supplier is not following the procurement contract.

B.

Request a revision of the procurement contract to include specifications for the parts.

C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.

D.

Review the procurement contract and ask the supplier to negotiate a solution.

Buy Now
Question # 477

An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the

project manager do to help improve the team's collaboration approach?

Options:

A.

Meet with the human resources (HR) department to ask for team support.

B.

Follow the process of the most successful team in the organization.

C.

Compare the team's velocity with other teams in the organization.

D.

Focus on the team's engagement during the next retrospective meeting.

Buy Now
Question # 478

A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued

Options:

A.

Schedule a meeting with critical stakeholders to review the issue and decide on the next steps

B.

Put the project on hold and release the resources until the issue is resolved

C.

Inform the product owner and log the issue in the risk register to monitor closely for next steps.

D.

Contact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.

Buy Now
Question # 479

A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members

What is the cause for this communication gap?

Options:

A.

The project sprint board has not been updated

B.

Daily standup meetings were not held or enforced

C.

The project status dashboard has not been updated

D.

The communications management plan has not been developed

Buy Now
Question # 480

A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project

What should the project manager do first to determine a governance approach for the project?

Options:

A.

Consult a subject matter expert (SME) as to the best governance policies, procedures, and guidelines to be used by the project

B.

Consult with team members and stakeholders to determine whether the organization has any informal governance policies procedures, and guidelines

C.

Choose either a predictive or agile framework best suited to the nature of the project, and use this framework as the basis for project governance policies, procedures, and guidelines

D.

Coach the self-managing team to produce tailored governance policies, procedures and guidelines for the project

Buy Now
Question # 481

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?

Options:

A.

Review the project scope and negotiate with the contractor

B.

Refuse the offer as it is included in the initial project scope

C.

Review the project costs and communicate this to the project sponsor

D.

Submit a change request to approve the offer

Buy Now
Question # 482

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

Options:

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Buy Now
Question # 483

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.

What training should the project manager choose for their team to help with this situation?

Options:

A.

Communication training

B.

Negotiation training

C.

Emotional intelligence training

D.

Agile training.

Buy Now
Question # 484

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

Options:

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample

Buy Now
Question # 485

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

Options:

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

Buy Now
Question # 486

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?

Options:

A.

Identify the problem's root causes and define the ground rules with all project team members to minimize interferences

B.

Hire a coach to help all project teams to improve their abilities to solve problems ontheir own.

C.

Reunite with the project team members affected and tell them not to reduce the team's capacity

D.

Recommend to the project team members that they should improve their planningand make their stones smaller

Buy Now
Question # 487

A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.

What should the project manager do?

Options:

A.

Wait for the team to identify and solve the problem independently.

B.

Move the team member to another task that is more skill appropriate

C.

Have a confidential discussion with the team member to identify the root cause

D.

Start a discussion with all team members to help resolve the issues

Buy Now
Question # 488

The project charter was just approved and the project sponsor has given permission to proceed with the project The program manager has confirmed that one of the requested key resources is also needed on another project at the same time This will affect project delivery

What should the project manager do?

Options:

A.

Pay overtime to key resource to get the work done outside of working hours

B.

Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects

C.

Speak with the client to see if the project delivery deadline can be delayed due to resource availability

D.

Talk to the program manager and about prioritizing this project over other projects so the key resources are available

Buy Now
Question # 489

A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using

What should the project manager have done to avoid this issue?

Options:

A.

Referred to the communications management plan

B.

Validated the issue log

C.

Validated the project artifacts

D.

Performed expert judgment

Buy Now
Question # 490

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?

Options:

A.

Assign the tasks to another resource, and ask the resource to work double shifts

B.

Update the schedule to reflect the project's changes in duration

C.

Ask human resources (HR) for a replacement, and update the nsk register

D.

Update the resource management plan and resource allocation chart accordingly

Buy Now
Question # 491

Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?

Options:

A.

The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate

B.

Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator

C.

The team facilitator uses historical data and arrives at an estimate based on the nature of the project.

D.

The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate

Buy Now
Question # 492

The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.

What two actions can the project manager take to be more cost effective? (Choose two)

Options:

A.

Conduct a stakeholder analysis.

B.

Reinforce team communication.

C.

Update the project management plan with the new timeline

D.

Adopt an incremental approach

E.

Leverage work between team members

Buy Now
Question # 493

Drag the to the correct scenario on the right

Options:

Buy Now
Question # 494

A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?

Options:

A.

Start developing a business case.

B.

Start a strengths, weaknesses, opportunities and threats (SWOT).

C.

Engage stakeholders and allocate resources

D.

Gather requirements from stakeholders

Buy Now
Question # 495

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

Options:

A.

Mark the product backlog completion status and update the communications management plan.

B.

Ensure that knowledge transfer activities are executed as planned

C.

Release the resources and plan for a project completion celebration.

D.

Hold a steering committee meeting to inform them of the project completion

Buy Now
Question # 496

The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?

Options:

A.

Review the project goal diagram with the team.

B.

Perform a stakeholder evaluation

C.

Confirm which templates the team should be using

D.

Review the risk management plan

Buy Now
Question # 497

A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.

What should the project manager do?

Options:

A.

Speak with peers about the need for a project charter

B.

Develop the project charter and send it for approval

C.

Explain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities

D.

Agree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan

Buy Now
Question # 498

A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?

Options:

A.

Conduct a stakeholder analysis to identify how regional policies may influence needs

B.

Request relevant stakeholders to conduct an analysis and reach consensus independently

C.

Conduct a project scope review workshop with relevant stakeholders.

D.

Conduct project planning meetings in one location with relevant stakeholders

Buy Now
Question # 499

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch

What should the project manager do to realize benefits?

Options:

A.

Add an entry in the risk log

B.

Implement the changes

C.

Review target benefits.

D.

Improve the team's velocity

Buy Now
Question # 500

Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?

Options:

A.

Explain to the managers that the contradicting requirements are being considered for implementation in the project

B.

Explain to the managers that only one of the two requirements can be implemented, and submit a change request,

C.

Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable

D.

Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits

Buy Now
Question # 501

A company wants to increase the commercial value of one of its products in a highly competitive market In order to do this, the company commissions a project to create a prototype The team constructs the prototype incrementally Which action should the project manager take as a priority?

Options:

A.

Emphasize the use of Kanban methodology.

B.

Ensure the project sponsor is aware of the go-to market date

C.

Deliver business value as soon as possible

D.

Implement a plan-do-check-act (PDCA) cycle

Buy Now
Question # 502

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

Options:

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Review the lessons learned from the previous project

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Create a lessons learned document for the initiation phase

Buy Now
Question # 503

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

Options:

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2025 Version)
Last Update: Nov 20, 2025
Questions: 2040
PMP pdf

PMP PDF

$139.65  $399
PMP Engine

PMP Testing Engine

$157.15  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$209.65  $599