Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 454

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

Options:

A.

Check if the budget can cover the enhancement

B.

Accept the request because it came from the project sponsor

C.

Refuse the project sponsor ' s request because it is out of scope

D.

Validate the proposed change ' s impact on the project.

Buy Now
Question # 455

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

Options:

Buy Now
Question # 456

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project ' s performance and wants to take steps to help the project succeed. What should the project manager do?

Options:

A.

Evaluate the project risk and try to replace the project with another one within the organization.

B.

Inform the project sponsor about the risk and try to convince them to withdraw the project.

C.

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.

D.

Continue executing the project using the project manager ' s usual methods as all projects are unique.

Buy Now
Question # 457

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.

B.

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.

C.

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder ' s final product.

D.

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.

Buy Now
Question # 458

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

Options:

A.

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.

B.

Document the request and escalate to upper management to consider a modification of the project charter.

C.

Agree on a predictive approach, but apply agile concepts under the project management umbrella.

D.

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

Buy Now
Question # 459

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

Options:

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

Buy Now
Question # 460

A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.

Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.

The company asked the project manager to explain the value gained by using an agile process.

How should the project manager respond?

Options:

A.

Early value cannot be achieved until the product is fully released.

B.

Early value can be gained by testing the most important features in the initial stages to fix deviations.

C.

Early value will be gained only if beta products can be released to the market.

D.

Early value will be gained only if the speed can be increased to release the product to the market.

Buy Now
Question # 461

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

Options:

A.

Reschedule the project execution date.

B.

Continue project execution using the current blueprints from the client.

C.

Escalate this issue to the project sponsor

D.

Consult with the client to determine if project execution should be continued.

Buy Now
Question # 462

A year after implementing a policy change to improve diversity and inclusion within two teams, there is increasing conflict within the company What should have been done to prevent this conflict?

Options:

A.

The organization should have introduced the concept of diversity broadly

B.

The leadership team should have worked closely with the marketing team to get insight on diversity

C.

Organization-wide diversity training should have been provided to the workforce

D.

The critical departments in the organization should have been involved in this exercise

Buy Now
Question # 463

At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.

What should have been done to avoid this situation?

Options:

A.

The acceptance criteria should have been properly defined in the contract

B.

The client requirements should have been clearly defined in the contract

C.

The Manage Quality process should have been appropriately conducted

D.

The project manager should have reviewed the standard industry defect rate

Buy Now
Question # 464

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.

Which release strategy should the project manager recommend?

Options:

A.

A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity

B.

An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country

C.

A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues

D.

A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time

Buy Now
Question # 465

A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested

in the product design.

How should the project manager deal with this situation?

Options:

A.

Escalate the issue to the project sponsor and seek assistance.

B.

Engage the project stakeholder and ensure all requirements are captured.

C.

Review the stakeholder engagement plan and communication strategy.

D.

Review the product requirements and update the stakeholder register.

Buy Now
Question # 466

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project ' s health?

Options:

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.

B.

Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.

C.

Ask the project managers to report on their projects using a Kanban board format.

D.

Request the program managers to be more accurate when presenting status reports.

Buy Now
Question # 467

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?

Options:

A.

Stop the meeting and reschedule for another time with a more concise presentation.

B.

Set up information review sessions before reconvening another approval session.

C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.

D.

Obtain approval as fast as possible and close the meeting.

Buy Now
Question # 468

A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.

What should the project manager do to ensure the velocity is under control?

Options:

A.

Ask the product owner to look at a minimum of four to eight iterations and replan the velocity for the next iteration based on the team ' s current performance.

B.

Ask the scrum master to plug gaps in the team ' s performance by adding a team member to compensate for the velocity decrease.

C.

Request that the team improve their cycle time to compensate for the velocity decrease.

D.

Request the team to improve the lead time, cycle time, and response time individually and track closure.

Buy Now
Question # 469

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member ' s concerns?

Options:

A.

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.

Provide direction to the team lead on how to resolve the issue with the team member directly.

Buy Now
Question # 470

One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization

How should the project manager acknowledge this team member’s commitment?

Options:

A.

Send this person to a meeting to negotiate the scope with the client

B.

Appreciate this team member’s performance throughout the project life cycle

C.

Promote this team member to a coaching role after this project is completed

D.

Document it in the team member’s end of year performance review

Buy Now
Question # 471

Drag the items on left side to the matching term within the correct project.

Options:

Buy Now
Question # 472

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?

Options:

A.

Assign the tasks to another resource, and ask the resource to work double shifts

B.

Update the schedule to reflect the project ' s changes in duration

C.

Ask human resources (HR) for a replacement, and update the nsk register

D.

Update the resource management plan and resource allocation chart accordingly

Buy Now
Question # 473

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

Options:

A.

Proceed with the project without allowing scope creep to occur

B.

Use the contingency funds to provide support for the requested projects

C.

Cancel the project since the stakeholder ' s request is out of scope

D.

Inform the sponsor and document the request in the stakeholder engagement plan

Buy Now
Question # 474

A few months into a project, several schedule issues have emerged Drag the schedule problems on the left to the specific tools on the right that if implemented during schedule development could have prevented the issues.

Options:

Buy Now
Question # 475

How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?

Options:

A.

Clarify project benefits with the sponsor.

B.

Identify the goal of each work product

C.

Perform integration testing of each release

D.

Include the entire project team in testing

Buy Now
Question # 476

A new team member has joined an agile project, replacing a team member who recently left The project team needs the new team member to speed up their ability to contribute effectively to the project

What should the project manager do to help in this situation?

Options:

A.

Assign the new team member the same tasks that were assigned to the previous team member who they replaced

B.

Schedule knowledge transfer sessions and assign less complex tasks to the new team member

C.

Send technical documentation to the new team member and schedule training for the next iteration.

D.

Have the new team member complete all of the company’s mandatory training

Buy Now
Question # 477

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

Options:

A.

Escalate the issue to the management team for their review and guidance

B.

Create a survey template to collect feedback from stakeholders to reach an agreement

C.

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.

D.

Leverage expert judgment to determine the requirements that should be considered

Buy Now
Question # 478

As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change

What should the project manager do?

Options:

A.

Conduct meetings with resistant members to facilitate smooth project implementation

B.

Meet with the team on a regular basis to ensure they are aware of changes.

C.

Influence the team to communicate any changes

D.

Check with the

Buy Now
Question # 479

During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?

Options:

A.

Ask the new team member to follow the team ground rules.

B.

Ask an experienced team member to identify a replacement

C.

Ask the new team member to reassess their own capabilities

D.

Ask an experienced team member to coach the new team member

Buy Now
Question # 480

A stakeholder is requesting that the project manager share project status updates

on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?

Options:

A.

Start sending status updates to this stakeholder based on the request.

B.

Ask the stakeholder ' s manager if the stakeholder can be added to the list.

C.

Review the stakeholder engagement and communications management plans.

D.

Escalate the stakeholder’s request to the project sponsor.

Buy Now
Question # 481

A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond ' ?

Options:

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance

B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework

C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance

D.

Explain to the stakeholder that the stakeholder engagement plan requires theirattendance at all reviews

Buy Now
Question # 482

The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements

How should the project manager address this situation?

Options:

A.

Ask the team to include the compliance requirement in the current sprint and deliver it.

B.

Add the new compliance requirement to the backlog as the technical team does not have any capacity.

C.

Include the compliance lead in the stakeholders list and wait for the next status meeting

D.

Collaborate with the compliance team member to review and prioritize the requirement’s delivery

Buy Now
Question # 483

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

Options:

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Buy Now
Question # 484

A team is working on implementing a communications system when the client says that they are considering closing the project. The project manager schedules an urgent meeting with the client to understand why the project is at risk Which two tools or techniques can the project manager use to influence the client’s decision to keep the project active? (Choose two)

Options:

A.

Alternatives analysis

B.

Voting

C.

Cost-benefit analysis

D.

Multi-criteria decision making

E.

Autocratic decision making

Buy Now
Question # 485

A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch

On what should the project manager focus?

Options:

A.

Ensuring that the team is also focused on the overall change management plan

B.

Determining and aligning performance indicators that will help in assessing successful delivery

C.

Planning for regular project updates to cover the status of critical deliverables

D.

Ensuring that the scope management plan is in place to cover all related objectives

Buy Now
Question # 486

A project manager is working with an agile team. A key stakeholder who does not

join the sprint planning session is very unhappy, as the delivery date for the final product has

been pushed back three times. What should the project manager do?

Options:

A.

Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.

B.

Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.

C.

Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.

D.

Secure some additional funding to recruit more resources to the project team to enable faster delivery.

Buy Now
Question # 487

An agile project team is looking to develop quality standards for a project How should the project manager coach the team?

Options:

A.

Determine the tools and techniques suitable for the project and ensure that testing is done early and continuously.

B.

Inform the team that user acceptance testing is required to ensure that the product owner accepts the solution

C.

Insist that test-driven development is implemented along with the automated testing

D.

Ensure that the definition of done (DoD) is provided when the product owner agrees that all acceptance criteria have been met for the user story

Buy Now
Question # 488

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

Options:

A.

Ask the stakeholders about the priority of this change

B.

Ask the product owner to review the product backlog

C.

Ask the team members to analyze the impact of this change

D.

Ask the sponsor to approve the change request

E.

Ask the team members to include the change in the next iteration

Buy Now
Question # 489

A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach. What should the project manager do to ensure full compliance of quality requirements during the execution phase?

Options:

A.

Analyze the quality requirements.

B.

Plan quality management

C.

Continually survey the quality of the deliverable

D.

Set up quality policies and procedures

Buy Now
Question # 490

During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization

What should the project manager do first?

Options:

A.

Update project documents to include adaptive tools and artifacts and plan the first iterative session

B.

Contact the project sponsor and request new team members who are familiar with adaptive projects

C.

Confirm team capabilities before introducing adaptive tools and artifacts to the project

D.

Freeze the design stage and look for an external resource to run iterative design at extra cost

Buy Now
Question # 491

The project team finds that the latest delivery from a vendor is missing a critical component, which will likely delay the project in split of corrective measures. What should the project manager do to communicate this message?

Options:

A.

Ask the vendor to identify the stakeholders affected, create an action plan and determine an implementation date

B.

Draft a warning letter to the vendor ask internal stakeholders to comment, and solicit stakeholder support to hold the vendor accountable

C.

Identify the worst-case scenario, put it into the project risk register, share the register with all project stakeholders, and raise an alert.

D.

Contact department managers who are identified as stakeholders, solicit concern, and provide updates to the situation

Buy Now
Question # 492

A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done

What kind of leadership style should the project manager use at this stage?

Options:

A.

A directive style that makes decisions for the group to reach early outcomes

B.

A leadership style that coaches people who want help and fosters greater team collaboration

C.

A passive leadership style that allows the team to self-organize until the norming stage is reached

D.

A democratic style that uses techniques where majority opinion prevails

Buy Now
Question # 493

A company has a lot of experience with predictive projects The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.

What should the project manager do?

Options:

A.

Prepare and submit a status report to the steering committee to update performance monitoring

B.

Determine the data to be monitored during the project as well as the expected performance and targets.

C.

Update the communications management plan to consider performance review meetings with the project stakeholders

D.

Conduct reviews with stakeholders to discuss the potential benefits the approach may have to the project

Buy Now
Question # 494

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?

Options:

A.

Revisiting the project management plan to ensure deliverables are on time

B.

Increasing the frequency of project update meetings to keep stakeholders informed

C.

Revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders

D.

Reviewing the business case and identifying gaps within scope

Buy Now
Question # 495

During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?

Options:

A.

Include stakeholders during daily standup meetings to monitor progress.

B.

Validate acceptance criteria with stakeholders prior to backlog refinement

C.

Avoid including stakeholders in iteration reviews.

D.

Create a requirements traceability matrix and distribute it accordingly

Buy Now
Question # 496

The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project

What should the project manager do to reduce negative impacts to the project?

Options:

A.

Modify the communications management plan to account for regional differences

B.

Conduct cultural awareness seminars

C.

Hold a virtual meeting to discuss the political environment.

D.

Conduct a multigenerational management training session

Buy Now
Question # 497

A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using

What should the project manager have done to avoid this issue?

Options:

A.

Referred to the communications management plan

B.

Validated the issue log

C.

Validated the project artifacts

D.

Performed expert judgment

Buy Now
Question # 498

The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies

What should the project manager do?

Options:

A.

Make sure the project team is aware of all agile techniques

B.

Skip the training because the team already understands agile

C.

Ensure the team has a common understanding of agile

D.

Teach one agile methodology fully and completely

Buy Now
Question # 499

A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog

What should the project manager do?

Options:

A.

Push the team to deliver more so that the modules are developed and rolled out according to management ' s request

B.

Speak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined

C.

Have the team work toward the tighter deadline so that integration will be easier.

D.

Speak to the team and slow the current pace to ensure the team is in alignment with the release date

Buy Now
Question # 500

A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion

What are two issues that these actions by the project manager could cause? (Choose two)

Options:

A.

A lot of discussions that yield no results or possibly too many results

B.

A lack of direction and motivation for the team in the workshop

C.

Lessons learned from other teams to not be considered

D.

Time management plan for the retrospective workshop to not be updated

E.

A focus on the negative and a disinterest in further improvements

Buy Now
Question # 501

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.

How should the project manager plan the delivery of the project?

Options:

A.

Wait for the requirements to be more clear before any further action is taken on the project

B.

Ignore the unclear requirements and focus on the delivery plan of the project

C.

Escalate the issue of unclear requirements to the management team and wait for final authorization

D.

Break down the requirements and prioritize the requirements into iterative work packages

Buy Now
Question # 502

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid

What should the project manager do?

Options:

A.

Add nonpayment to the issue log and keep tracking payments

B.

Hold a meeting with the client to address the issue

C.

Review past projects for payment-related lessons learned

D.

Conduct a meeting with the project team to update the procurement management plan

Buy Now
Question # 503

A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?

Options:

A.

Created a communications management plan that outlined the method of communicating to stakeholders.

B.

Ensured that the company culture encourages changes before accepting the project

C.

Encouraged leadership to discuss the change with departments that are typically resistant to change

D.

Involved stakeholders from all levels of the company so everyone understands the change

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMBOK 7th Version)
Last Update: Jul 5, 2026
Questions: 2196
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599