A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables. How should the project manager respond?
A project manager is tasked with developing a coaching model to support and recognize team members ' growth.
What should the project manager consider when defining their coaching strategy?
When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined. What should the project manager do?
During project initiation meetings, the project manager of a 9-month project states that a specific task would be out of schedule. At the project
kick-off meeting, a key project stakeholder strongly objects, stating that this task is the key value of the project and should be completed on time.
What should the project manager do to reduce the chances of having a strong rejection from stakeholders during the project initiation stage?
A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within
the organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the
projects to use more agile methodologies.
Before mandating any agile methods to be used in a project, what should the project manager do first?
During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product ' s operating procedures.
What should the project manager do?
A project manager has expertise in the technical domain. The project manager frequently demonstrates unacceptable behavior toward other team
members; however, when confronted, the project manager denies this behavior.
What is the reason for the project manager ' s behavior?
An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete the job successfully. What should the project manager do to reduce the risk of project failure?
A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.
What should the project manager do?
A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this project?
A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The
resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.
What should the project manager do?
A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?
There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.
How should the project manager handle this situation?
A project manager is leading a long-term project, executed in stages, to set up a complex communications network in many rural areas. The project is being executed in stages.
What should the project manager do to ensure that monetized business value is generated as planned?
A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose two)
A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be
required 3 months prior to the project ' s finish date. During project execution, it was determined that the contract was required immediately.
What should project manager do?

An agile team has sized all of the features for the release. Using the table above, how many sprints will it take to complete this release if the team is expecting to have a
velocity of 10 story points per sprint?
A project manager is working as a servant leader for a pilot project to adopt agile practices. After three sprints, the team demos the product to the
main stakeholders, but receives negative feedback about the product ' s features. The team feels that all the features met the acceptance criteria
defined by the product owner and does not understand what went wrong.
How should the project manager mitigate the product rejection?
During daily team standup meetings, team members constantly ask about which tasks they should focus on first. How should the project
manager ensure the team is fully productive?
A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.
What should the project manager do to address the issue?
A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.
What should the project lead do?
A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project
manager knows this team member could add value to the project.
What should the project manager do to get the most value from this team member?
A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in
innovative ways without any need for encouragement. However, the engineer declines the project manager ' s invitation to join the new project.
What is the most likely reason for the engineer ' s refusal to work on the project?
After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work (SOW).
These changes would improve the project outcome.
What should the project manager do next?
A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting all together. What should the project manager do?
A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.
What should the project manager do next?
A project team ' s performance is being impacted by impeding internal procedures that are affecting the progress of activities and team autonomy. What should the project
manager do first to address this situation?
A project manager finds it challenging to comply with standardized processes for knowledge transfer. The project teams and stakeholders are scattered around field sites,
the office, and remote locations. In addition, some team members have limited access to the electronically shared files.
How should the project manager manage this challenge?
A town wants to build a community center and has appointed a project manager. A site was found, and all of the necessary approvals and governance were completed. When the project kick-off was held, it was discovered that a local farmers ' group was not consulted, and they use the site for a monthly market.
What should the project manager do to move forward with the project?
A team needs to implement a mandatory compliance regulation in a product, which is required for its release. While nearing the product release, when completeness was
being verified, it was found that the compliance part was not implemented in the project.
What should the project manager do next?
A team has had issues with behavior on an ongoing project, which is causing conflicts. As a result, the team is losing momentum and falling
behind in its sprints.
How should the project manager handle this situation?
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client ' s needs.
What should the project manager do?
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool ' s scalability to support their business needs.
How should the project manager resolve this conflict and reach a consensus?
An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist ' s expertise. The project team is actively seeking assistance in order to complete the job on time.
What should the project manager do to help the project team?
A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the
original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.
What should the project manager do to resolve this conflict?
At the end of a project ' s initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.
How should the project manager reply?
An enthusiastic, newly hired vice-president has been assigned as the product owner for a digital transformation project. The project manager
advises the product owner that some of the functional requirements are not aligned with the chief information technology officer ' s (CTO) strategy.
The product owner tells the project manager that the CTO is not part of the project and should not be engaged at this moment.
What should the project manager do?
A project manager is managing a project in the execution phase, which was agreed upon with the sponsor. However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team ' s effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed to simplify the project.
How should the project manager handle the situation?
A project manager leads a project that implements a new process throughout the organization. The rollout is done in stages and the project manager planned a demonstration for the pilot business units. A manager from a business unit that is scheduled for a later date asks to be invited to the sprint review.
What should the project manager do?
A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?
A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the project manager do?
A project is starting its second iteration out of six. During the daily meeting, a team member asks for help. In order to finish a deliverable, an
approval from the design department will be needed.
What should the project manager do?
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring SO many iterations with a risk of not reaching the mandatory delivery date.
Which approach should the project manager use in this situation?
A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.
What should the project manager do next?
During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a
low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that
this could be a high risk for the project.
Which action should the project manager take?
A project manager is assigned to a major construction project. The project is critical to the city ' s population, and especially to the local government
official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include
aspects that the previous project sponsor did not support.
What should the project manager do next?
A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.
How can the project manager strategize the use of a hybrid approach to the organization?
An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.
How should the facilitator proceed?