Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 554

A project manager is reviewing the lessons learned for an historical project. The review identifies that the client's engineer was adamant that they review all changes, even those not identified in the contract.

How should the project manager deal with this when planning the project?

Options:

A.

Ensure the change management plan highlights this requirement to prevent future issues.

B.

Update the project charter with this information regarding change management.

C.

Update the project risk register to identify this risk and describe how to mitigate the issue.

D.

Talk with the client to ensure they are aware of the change management procedure.

Buy Now
Question # 555

A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a

previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.

Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions.

B.

Recognize the stakeholders skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.

C.

Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.

D.

Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.

Buy Now
Question # 556

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?

Options:

A.

Ensure the activities of this team member are distributed across the project team.

B.

Assess a mechanism for knowledge transfer among the team members.

C.

Motivate the team member to stay by providing them with incentives.

D.

Ask human resources (HR) to counsel the team member to balance the workload.

Buy Now
Question # 557

A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.

What should the project manager do?

Options:

A.

Schedule a one-on-one meeting with the functional manager to prove the project is on time

B.

Listen carefully and show understanding of the growing needs of the functional manager.

C.

Admit that the functional manager is right and promise to rectify the situation immediately.

D.

Show the functional manager that the progress is on time based on the schedule.

Buy Now
Question # 558

A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?

Options:

A.

Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals

B.

Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.

C.

Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

D.

Secure approval of the prefeasibility study before proceeding with the feasibility activities.

Buy Now
Question # 559

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?

Options:

A.

Use a business case to model a sales pitch and gain consensus from the sponsors.

B.

Request help from the project sponsor to get support from the sales agents.

C.

Escalate the issue to senior management to gain team buy-in

D.

Explain the change benefits to the sales agents' manager to get their support.

Buy Now
Question # 560

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

Options:

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

Buy Now
Question # 561

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)

Options:

A.

Schedule weekly progress meetings with all three teams and have them take turns as key players.

B.

Plan for team members to temporarily work at each other's locations to better provide a sense of community.

C.

Update the communications management plan and encourage the teams to review it promptly and proactively.

D.

Create a status reporting template and share it with all team members before the day ends.

E.

Schedule daily meetings with each team to understand their progress and concerns in detail.

Buy Now
Question # 562

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

Options:

A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

B.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.

C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

D.

Create a record in the issue register and escalate the issue to the project steering committee.

Buy Now
Question # 563

When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a

result, the team ground rules favor these two team members.

What should the project manager have done to avoid this situation?

Options:

A.

Come to the meeting with suggested ground rules

B.

Ask all team members to send new ideas prior to the meeting

C.

Extend the meeting to allow everyone to speak

D.

Set expectations for contributions ahead of the meeting

Buy Now
Question # 564

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

Options:

A.

Meet with the project team to develop a proper resolution to the issue.

B.

Update the project artifacts to reflect the new deadlines reported.

C.

Request approval from the project sponsor to add more resources,

D.

Prepare documentation to explain the issue and communicate accordingly.

Buy Now
Question # 565

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

Options:

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.

Add more iterative techniques to improve stakeholder learning.

C.

Identify all the critical stakeholders during the project initiation.

D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Buy Now
Question # 566

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile

practices, which are relevant to the project.

What should the project manager do in order to gain buy-in from the different stakeholders?

Options:

A.

Organize a meeting with relevant stakeholders explaining the benefits of agile and the practices relevant for the project.

B.

Send the project management plan, which includes the suggested agile practices, to the stakeholders.

C.

Ask the project management office (PMO) to get buy-in from the stakeholders, because agile is an approach that differs from their previous

ways of working.

D.

Organize a meeting with a consultant to provide training to the stakeholders on agile practices.

Buy Now
Question # 567

A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to

water. What should the project manager do next?

Options:

A.

Hire local contractors who are familiar with the environment.

B.

Start project planning and develop the project management plan.

C.

Face the challenge immediately and start sending relief to the town.

D.

Process a change request for additional funding due to project urgency.

Buy Now
Question # 568

A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.

What should the project manager do?

Options:

A.

Conduct a performance review and define and document the goals for the team member.

B.

Clarify decisions and request that the project team follows the project manager's decisions.

C.

Understand what the team member wants and find possible opportunities to address it.

D.

Remove existing ground rules and create new ground rules that support the project manager.

Buy Now
Question # 569

In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The

discussion has intensified and the team members are not able to agree.

What should the project manager do next?

Options:

A.

Remove one of the team members from the project to improve team dynamics.

B.

Make a decision based on expert judgment as a project manager.

C.

Consider the view of each team member about the issue in order to reach consensus.

D.

Remove both team members since they are not productively adding to the team.

Buy Now
Question # 570

A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?

Options:

A.

Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.

B.

Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope

C.

Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack

D.

Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan

Buy Now
Question # 571

A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.

When should the value be demonstrated?

Options:

A.

After full development is completed

B.

When a major feature is completed

C.

At the end of each and every iteration

D.

When the sponsor approves the increment

Buy Now
Question # 572

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Options:

A.

Ask the product owner if some low-priority stories could be cut from the sprint.

B.

Continue with the sprint as the progress shows buffers for potential interruptions.

C.

Ask the project team to select any additional stories as they have additional capacity than planned.

D.

Continue with the sprint work as planned and keep monitoring.

Buy Now
Question # 573

A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

Options:

A.

Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.

B.

Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.

C.

Communicate the latest status to the steering committee and provide a demo of the features completed.

D.

Schedule routine demos on features completed and deliver a single product once all features are completed.

Buy Now
Question # 574

A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

Options:

A.

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.

Work with and assist the project sponsor in building and prioritizing the product backlog.

Buy Now
Question # 575

A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.

What should the project manager do?

Options:

A.

Allow collaboration to smooth out communication between team members.

B.

Add collaboration tools to the communications management plan.

C.

Escalate these communication challenges to the project sponsor.

D.

Organize a team meeting to resolve the communication challenges.

Buy Now
Question # 576

A project manager is reviewing the status of a large project with team members in different countries. Through the status review, the project

manager notices that one team is consistently behind schedule and their work often needs to be corrected.

What should the project manager do to improve the quality of this team's work?

Options:

A.

Evaluate the issue with the team to determine if they have the necessary skills to perform assignments.

B.

Review the issue with the project sponsor and work to reduce the scope for that team.

C.

Guide all team members and bring in external consultants to complete the work.

D.

Ask a local subject matter expert (SME) to assist the team in reviewing the project requirements.

Buy Now
Question # 577

A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager

discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The

remote team member feels they are not being adequately rewarded and recognized for their job.

What should the project manager do?

Options:

A.

Inform the human resource (HR) manager of this situation and ensure this news does not spread.

B.

Make arrangements with the resource's functional manager to relocate the team member to another existing project.

C.

Send a copy of the engagement contract to the remote team member and indicate that the team member is entitled to what is included in the

contract.

D.

Engage the remote team member, empathize with them, and let them know their contribution is appreciated regardless of their remote work status.

Buy Now
Question # 578

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

Options:

A.

Update the project charter with the new requirement.

B.

Add a risk to the risk register.

C.

Add it to the issue log as an ongoing issue.

D.

Review and validate the scope management plan.

Buy Now
Question # 579

A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.

What should the project manager do first to verify alignment?

Options:

A.

Ask the project team to delay the kick-off while resolving the concern.

B.

Request a copy of the project assumptions log for more insight.

C.

Meet with the project sponsor to obtain more information.

D.

Consult with the project team members to gain their opinions.

Buy Now
Question # 580

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

Options:

A.

The project is over budget and behind schedule.

B.

The project is under budget and on schedule.

C.

The project is under budget and behind schedule.

D.

The project is on budget and on schedule.

Buy Now
Question # 581

A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.

Which stakeholders should the project manager consult with first to manage interdependencies?

Options:

A.

Project sponsors

B.

Other project managers

C.

Business unit managers

D.

Program managers

Buy Now
Question # 582

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

Options:

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

Buy Now
Question # 583

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional

managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

Options:

A.

Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.

B.

Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.

C.

Request a meeting with the sponsor to change the scope to allow the development team to conduct testing.

D.

Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.

Buy Now
Question # 584

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

Options:

A.

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,

B.

Send emails with information about the project deliverables on the first day of the project.

C.

Connect with every location and check their preferred methods of communication.

D.

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.

Buy Now
Question # 585

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.

What should the project manager do?

Options:

A.

Inform the project sponsor about the problem faced by the team.

B.

Ask the product owner to write the specifications for the related user story.

C.

Organize an early retrospective with the team to analyze the problem.

D.

Facilitate a problem-solving session with the team to analyze the problem.

Buy Now
Question # 586

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

Options:

A.

Engage the functional managers to describe the project's impact to the team members directly.

B.

Provide team members with specific and clear instructions on the project objectives and tasks.

C.

Communicate the project's impact and plans to engage the project team throughout the project.

D.

Escalate the team's concerns and ask the project sponsor to change the team's composition.

Buy Now
Question # 587

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

Options:

Buy Now
Question # 588

A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.

What should the project manager do in this situation?

Options:

A.

Assess the impact of the stakeholder and engage properly.

B.

Escalate the stakeholder issue to the project sponsor.

C.

Develop a specific communications strategy for this stakeholder.

D.

Use interpersonal skills to gain stakeholder engagement.

Buy Now
Question # 589

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

Options:

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Buy Now
Question # 590

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

Options:

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

Buy Now
Question # 591

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?

Options:

A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog

B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints

C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration

D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks

Buy Now
Question # 592

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member's functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

Buy Now
Question # 593

At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?

Options:

A.

Defer all actions until the next workshop to keep the team focused on other higher priorities

B.

Follow up on each item as soon as possible to ensure timely completion and report the status to management.

C.

Review the critical path and update the project schedule with the newly identified tasks.

D.

Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.

Buy Now
Question # 594

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

Options:

A.

Incorporate the changes in the last sprint before the first release.

B.

Call for an internal meeting to discuss the changes and their value.

C.

Ask the product owner to prioritize the backlog with the project team.

D.

Request the scrum team to prioritize the product backlog.

Buy Now
Question # 595

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for

the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

Options:

A.

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.

Stakeholders who disagree with the project so as to proactively manage their expectations.

D.

Stakeholders who are supporting the project in order to obtain additional resources.

Buy Now
Question # 596

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

Options:

A.

Assign a development team member to have the responsibility of managing dependencies.

B.

Suggest that each project develops a high-level plan to monitor the dependencies

C.

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.

Continue the project with 2-week iterations as dependencies will be managed individually

Buy Now
Question # 597

During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.

How should the project manager help guide the lead developer?

Options:

A.

Advise the lead developer and team to consult with the project architect and for their development team leader.

B.

Reassign this work package to another area given the lead developer's concerns,

C.

Direct the lead developer to conduct a weighted evaluation of all products and solutions.

D.

Listen to the concerns and suggest that the lead developer and the team be empowered to recommend the best approach.

Buy Now
Question # 598

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

Buy Now
Question # 599

A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.

What should the project manager do?

Options:

A.

Design an updated status report.

B.

Request a meeting with the stakeholder.

C.

Escalate this to the project sponsor.

D.

Forward the project status reports.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2025 Version)
Last Update: Aug 22, 2025
Questions: 1988
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599